Velindre Hospital - CT Simulator

Project Details:
Client: Velindre NHS Trust 
Start Date: January 2021 
Completion Date: April 2021
Value: £350,000
Sector: Healthcare 


Project summary:
Working within the confines of the Velindre University Trust Hospital, BECT has remodeled a redundant CT Simulator room to form a new examination room and patient waiting area, as well as refurbishing several rooms and corridors within the unit.  

The works consisted of Strip out of all existing fixtures and fittings, creating new partitions and forming new openings, installation of all associated services. 


Project Teams:
Architect: HL Designs 
Employers Delegates: Lee Wakemans 
M&E Consultant: McCann & Partners
Form of Contract: NEC