Roof works nearing completion on both heritage buildings: Restoration of the historic roof structures is nearly complete, ensuring both buildings are weather-tight while retaining key architectural features.
Demolition works completed: All demolition activities have been successfully completed, allowing internal restoration and structural works to progress.
Façade mortar repairs at Cory’s nearing completion: Traditional repair techniques have been used to restore the original brick and stone façades, with works now swiftly progressing.
Concrete frame progressing rapidly: The new concrete frame is advancing at pace and will form the central structure connecting the two listed buildings as part of the project’s development.
Lime render application underway at Cory’s: Lime render works are progressing well, providing a breathable and historically appropriate finish to the building’s internal walls.
Heritage roof light restoration at Merchants Building: The existing roof light has been carefully restored, while retaining its original structure and character. Works are now nearing completion.