The project involves the development of a three-story extension to the existing hotel, adding 21 new beds and a new air conditioning system. As part of this expansion, two current bedrooms will be repurposed into an additional UA Bedroom and a Staff Team Room. The construction will feature a timber frame extension designed to align with the height of the existing hotel and will include, but is not limited to, the following key activities:

 

– Laying down the foundations

– Erecting the timber frame and superstructure

– Creating a link between the extension and the existing hotel

– Building internal partitions

– Installing, testing, and commissioning mechanical and electrical systems

– Carrying out complete decoration throughout the premises

– Adding internal and external signage

– Constructing a new A/C compound

– Reconfiguring the car park

– Implementing hard and soft landscaping

 

This comprehensive approach aims to enhance the overall functionality and appeal of the hotel.

Sector
Hotel
Value
£1.5 Million
Duration
26 Weeks
Client
Whitbread Group PLC